Manufacturing & Life Sciences

Hankook Tire Clarksville Plant Expansion

The Phase II expansion of Hankook Tire’s Clarksville, TN campus adds 2.2 million square feet of new production and support facilities to meet growing demand and improve manufacturing efficiency.

CHA is delivering design/engineering, labor, and project management services for a comprehensive fire protection package. This includes overhead wet systems, dry systems, deluge systems, and pre-action systems designed to protect commodities classified under Extra Hazard Group I and II. Two new diesel fire pumps and a 300,000-gallon water storage tank will support the fire protection infrastructure. Upon completion, a total of 71 systems will be installed across the main production building and surrounding ancillary facilities.

In addition to fire protection, the project integrates key building systems such as domestic plumbing, HVAC, process mechanical distribution (chilled water, compressed air, and steam), industrial electrical distribution, process controls, and fire alarm systems. These systems are critical to maintaining safe, efficient, and high-performance operations throughout the facility.

Project summary

2.2M SF

The expansion has  added 2.2 million square feet of new facilities.

71

A total of 71 systems provide fire protection.

300K

The project installed a 300,000-gallon water storage tank.

Talk to an expert

Johnathan Greathouse

Johnathan Greathouse
Vice President, Business Practice Leader

Get in touch

Johnathan has over two decades of experience specializing in fire protection systems design and project management. His expertise includes wet and dry sprinkler systems, pre-action systems, foam suppression, fire pumps, and standpipe systems. Johnathan has contributed to a variety of complex projects across commercial, industrial, and government sectors, consistently delivering reliable and efficient fire suppression solutions.